The Nou Mestalla installs the auxiliary scaffolding for the cable assembly prior to the lifting of the large roof structure

The project is progressing in the development of the façade and the stair towers

The Nou Mestalla continues progressing in its construction. The installation of the large roof is getting closer and closer and, today, new updates for its preparation can already be seen.

Currently, Valencia CF, together with FCC Construcción, is working on the assembly of this important structure that will cover the 70,044 seats that our new home will have from the summer of 2027.

The companies Horta Coslada and PFEIFER have already made considerable progress in the assembly of the auxiliary scaffolding for the installation of the traction ring cables, as well as in the stand protections for the deployment of the radial cables. In addition, progress is being made on the execution of the façade and the stair towers (the four in the north area and on the east side have been installed).

In recent weeks, progress has also been made on the roof support structure (‘bird nests’ on each pillar that pull and stretch the cables; the scaffolding and stand protections have been installed). At the same time, the compression rings have been assembled and the remaining pillars have been completed.